Installation Guide What Mark Learned Setting Up His Daikin 20 Ton System

When I first decided to upgrade my building’s HVAC, I knew it wasn’t going to be as simple as swapping out a home AC. Commercial systems—especially a 20 ton Daikin packaged unit—are a whole different beast. From crane lifts to electrical service upgrades, I learned a lot during this project. This guide walks through the full process of installing a 20 ton commercial AC system, step by step, so you know what to expect before taking the plunge.


🏢 Why I Chose the Daikin 20 Ton 14.2 IEER2 System

Before we get into the “how,” let’s talk about the “why.”

  • Size & Capacity: At 20 tons (240,000 BTUs), this Daikin model is designed for light commercial spaces like retail, offices, and small warehouses.

  • Efficiency: It carries a 14.2 IEER2 rating, which meets 2023–2025 Department of Energy standards for rooftop and packaged units (DOE efficiency standards).

  • Reliability: Daikin has a strong reputation for durability, which mattered since downtime costs me money.

  • Packaged Design: Everything is self-contained in one rooftop unit, which simplified ductwork and installation.


📐 Pre-Installation Planning: Site, Space & Power

1. Roof Structural Assessment

The first surprise? This unit weighs over 2,000 lbs. Before ordering, I had to bring in a structural engineer to confirm my roof could handle the load. They checked:

  • Beam spacing and reinforcement

  • Roof curb compatibility

  • Load distribution points

👉 If you skip this step, you could be looking at sagging roofs or denied building permits.

2. Clearances & Placement

Daikin specifies minimum service clearances (usually 36–48 inches on all service sides). You’ll want enough space for:

  • Opening panels

  • Filter changes

  • Coil cleaning access

Daikin’s commercial installation manuals are essential references.

3. Power Availability

This model runs on 460V, 3-phase, 60Hz. That meant checking:

  • My building’s existing electrical service

  • Transformer size

  • Breaker panel space

I had to work with my utility provider to confirm capacity. If your building only has single-phase service, you’ll need costly upgrades.


🧰 Tools, Equipment & Team Needed

No way around it—this is not a one-person job. Here’s what we needed:

  • Crane service (for rooftop placement)

  • Forklift or dolly (to move on the ground)

  • Licensed electricians (for high-voltage connections)

  • HVAC techs (for duct and controls)

  • Sheet metal crew (to fabricate and install transitions)

  • Safety gear: harnesses, PPE, lockout/tagout kits

👉 OSHA has strict guidelines for commercial HVAC installation safety.


🏗️ Delivery, Rigging & Crane Lift

When the Daikin unit arrived on a flatbed, it looked massive—almost the size of a car.

  1. Rigging Prep: We attached lifting lugs and spreader bars to avoid damaging the panels.

  2. Crane Coordination: Scheduled early morning before traffic. The lift required street permits.

  3. Setting on the Roof Curb: The curb had been installed a week earlier, sealed, and flashed for waterproofing.

Mark’s tip: Don’t skimp on the curb sealant—water leaks through the roof are expensive headaches.


🔌 Electrical & Power Requirements

This was one of the trickiest parts.

  • Disconnect Switch: Installed within sight of the unit as required by NEC code.

  • Conduit & Wire Size: Based on Daikin’s amp draw charts. For a 20-ton, it required heavy-gauge copper wiring.

  • Breaker Sizing: Coordinated with my electrician to meet both unit specs and building code.

  • Grounding: Proper grounding is critical to protect sensitive control boards.

Lesson learned: Always have an electrical permit pulled before starting. Inspectors will check.


🌬️ Ductwork, Airflow & Economizer Setup

This Daikin system connected directly to my building’s supply and return ductwork.

Duct Transitioning

  • Fabricated sheet metal to match the unit’s supply/return openings.

  • Installed flexible connectors to reduce vibration.

  • Ensured insulation was sealed to avoid energy loss.

Economizer Setup

Many 20-ton units come with an optional economizer for free cooling. Mine did.


🧑🔧 Controls, Thermostats & Integration

This was where the system met the smart controls I wanted.

Mark’s note: If you have multiple tenants or zones, zoning dampers are worth every penny.


✅ Testing, Balancing & Commissioning

After all hookups were complete, the commissioning process began.

  1. Leak Check: Pressurized refrigerant circuit and duct system.

  2. Power-Up Sequence: Verified voltage and phase rotation.

  3. Airflow Balancing: Used an anemometer to balance CFM to each zone.

  4. Functional Testing: Tested cooling stages, economizer, and fan speeds.

Commissioning took about half a day but was critical for efficiency and warranty validation.


🧽 Post-Install Cleanup & First Maintenance Steps

The last steps were surprisingly important:

  • Removed construction debris from ducts.

  • Logged system serial numbers for warranty.

  • Scheduled first filter change after 30 days (construction dust clogs filters fast).

  • Signed up for a quarterly maintenance plan.

For more info, Daikin recommends following their commercial maintenance guidelines.


💡 Lessons Learned: My Personal Takeaways

After going through the installation, here are my biggest lessons:

  • Plan early. Structural and electrical assessments take weeks.

  • Budget realistically. Crane costs, permits, and electrical upgrades add up.

  • Hire pros. This isn’t a DIY job—too many code and safety factors.

  • Document everything. From load calcs to permit numbers, paperwork saves headaches.

  • Schedule downtime. The building was without AC for a full day—coordinate with tenants or staff.


 

Mark callahan

Leave a comment

All comments are moderated before being published